Home » » KAMATI YA KUDUMU YA BUNGE YA MIUNDOMBINU YATEMBELEA MRADI WA UJENZI WA DARAJA LA JP MAGUFULI ( KIGONGO – BUSISI)

KAMATI YA KUDUMU YA BUNGE YA MIUNDOMBINU YATEMBELEA MRADI WA UJENZI WA DARAJA LA JP MAGUFULI ( KIGONGO – BUSISI)

Written By CCMdijitali on Saturday, March 19, 2022 | March 19, 2022

 






KAMATI YA KUDUMU YA BUNGE YA 

MIUNDOMBINU YATEMBELEA MRADI WA

 UJENZI WA DARAJA LA JP MAGUFULI

 ( KIGONGO – BUSISI)


•Urefu wa Daraja Km 3.2 na Barabara unganishi Km 1.66

•Ajira za wazawa 753 kati ya 809

•Mashimo ya nguzo za msingi 382 yamekamilika kati ya 804 (47.51%)

•Zege la kufunika nguzo za msingi 13 zimekamilika kati ya 65 (20%)

•Nguzo za kwenye maingilio ya Daraja 1 imekamilika kati ya 2 (50%)

•Nguzo za katikati ya daraja 4 kati ya 65 zimekamilika (6.15%)

•Nguzo za msingi 358 zimejengwa kati ya 804 (44.53%)

•Utekelezaji wa mradi umefika 41.59%

•Gharama za mradi ni Shilingi Bilioni 716.3

•Mradi unatarajia kukamilika Februari, 2024

#kaziiendelee๐Ÿ”ฅ๐Ÿ”ฅ๐Ÿ‡น๐Ÿ‡ฟ๐Ÿ‡น๐Ÿ‡ฟ๐Ÿ‡น๐Ÿ‡ฟ๐Ÿ’ช๐Ÿฟ๐Ÿ’ช๐Ÿฟ๐Ÿ’ช๐Ÿฟ๐Ÿ’ช๐Ÿฟ
@bunge.tanzania

Share this article :
 
Support : #BegaKwaBegaNaMamaSamia | JAK | CCM Arusha
Copyright © 2011. CCM Dijitali - All Rights Reserved
Template Created by Creating Website Published by Jasper K
Proudly powered by Blogger
Link